Pert(Min,Most likely,Max)

Pert equations

 

 

The PERT (aka BetaPERT) distribution gets its name because it uses the same assumption about the mean (see below) as PERT networks (used in the past for project planning). It is a version of the Beta distribution and requires the same three parameters as the Triangular distribution, namely minimum (a), most likely (b) and maximum (c). The figure below shows three PERT distributions whose shape can be compared to the Triangular distributions:

 

 

 

 

 

Uses

The PERT distribution is used exclusively for modeling expert estimates, where one is given the expert's minimum, most likely and maximum guesses. It is a direct alternative to a Triangular distribution, so a discussion is warranted on comparing the two:

 

Comparison with the Triangular distribution

The equation for the PERT mean (above) is a restriction that is assumed in order to be able to determine values for a1 and a2. It also shows how the mean for the PERT distribution is four times more sensitive to the most likely value than to the minimum and maximum values. This should be compared with the Triangular distribution where the mean is equally sensitive to each parameter. The PERT distribution therefore does not suffer to the same extent the potential systematic bias problems of the Triangular distribution, that is in producing too great a value for the mean of the risk analysis results where the maximum for the distribution is very large.

 

The standard deviation of a PERT distribution is also less sensitive to the estimate of the extremes. Although the equation for the PERT standard deviation is rather complex, the point can be illustrated very well graphically. The figure below compares the standard deviations of the Triangular and PERT distributions with minimum =0, maximum = 1, and varying most likely value.

 

 

The observed pattern extends to any {a,b,c} or {min,ml,max} set of values. The graph shows that the PERT distribution produces a systematically lower standard deviation than the Triangular distribution, particularly where the distribution is highly skewed (i.e. b is close to the minimum or maximum). As a general rough rule of thumb, cost and duration distributions for project tasks often have a ratio of about 2:1 between the (maximum - most likely) and (most likely - minimum), equivalent to b = 0.3333 on the figure above. The standard deviation of the PERT distribution at this point is about 88% of that for the Triangular distribution. This implies that using PERT distributions throughout a cost or schedule model, or any other additive model with similar ratios, will display about 10% less uncertainty than the equivalent model using Triangular distributions.

 

You might argue that the increased uncertainty that occurs with Triangular distributions will compensate to some degree for the over-confidence that is often apparent in subjective estimating. The argument is quite appealing at first sight but is not conducive to the long term improvement of the organization's ability to estimate. We would rather see an expert's opinion modeled as precisely as is practical. Then, if the expert is consistently over-confident, this will become apparent with time and his/her estimating can be re-calibrated.

 

 

 

 